Physical server move in Ashburn, VA
Scheduled Maintenance Report for DNSimple
Completed
Everything looks to be up and running and responding. As always, please email support@dnsimple.com if you're seeing any issues with the development API.
Posted Oct 25, 2016 - 17:45 UTC
Verifying
The systems are back online and we're double checking that all the services are responding correctly before we remove the maintenance page. We hope to be back very shortly and thank you again for your patience.
Posted Oct 25, 2016 - 17:00 UTC
Update
The servers are being physically moved now and the API and Web should now be responding with 503 status codes. When the move is complete we will be verifying and updating the systems before putting them back into production. Thank you again for your patience.
Posted Oct 25, 2016 - 15:38 UTC
In progress
We're preparing to disable web and API traffic to Sandbox ahead of the physical move.
Posted Oct 25, 2016 - 15:18 UTC
Scheduled
Our hosting provider is going to be physically moving our servers in the Ashburn, VA data center into a new cabinet within the same data center which will cause a full outage of our Sandbox environment for developers. During this window, our Sandbox environment will be responding with 503s on both the web and API side. We're budgeting 4 hours for this migration to account for any issues with networking that may arise.
Posted Oct 22, 2016 - 01:18 UTC